1. Plan Project Stages 
back to roadmap
 
 
2. Water Delivery Plan
    - Valley Pivot Design Guide: Soil, Water, and Crop Considerations (Link broken - https://unl.box.com/s/dckvdzporwta49gb5bpibto53nni1631)
 
    - Ground Water
    
        - Obtain groundwater well construction permits (if required)
        
        
 
        - Contract well driller to drill and install wells
        
        
 
        - Oversee construction of water wells to project specifications.
        
        
 
        - Purchase and acquisition of water well pumps, column pipe and electrical wire based on project specifications.
        
            - Centrifugal Pumps pg 9-19 of “Understanding Pump Controls and Wells” (Link broken - https://unl.box.com/s/jc5jeg5s7ubft7flz4cf5j9z5xed6fvs)
 
            - Dictating pump type based on water source pg 24 “Understanding Pump Controls and Wells” (Link broken - https://unl.box.com/s/qwgmjtunfv4kkraqd9pigw4mbscctitd)
 
            - Choosing a Pump pg 27-28 “Understanding Pump Controls and Wells” (Link broken - https://unl.box.com/s/wxhkxtrf10ip030cu8wem8przcuv9mtr)
 
            - Pump Performance Test pg 77 “Understanding Pump Controls and Wells” (Link broken - https://unl.box.com/s/vpfayigatyv42mizxf153guzhc2p23wa)
 
            - Performance Testing Procedure for Centrifugal Pumps (Link broken - https://www.scribd.com/doc/61108581/Performance-Testing-Procedure-for-Centrifugal-Pumps)
 
        
         
        - Oversee completion of well and installation and startup of water well pumps
        
            - Pumps & Controls pg 137 (Link broken - https://unl.box.com/s/yykpx0jrtxg3lnj7zngxmyk6f7qfoky2)
 
            - Water Resource Design: Cascade Earth Sciences (Link broken - http://cascade-earth.com/home/markets-and-services/services/water-resource-services)
 
            - Centrifugal Pumps: The Basics
 
        
         
    
     
    - Surface Water
    
        - Obtain groundwater well construction permits (if required)
        
            - South Africa Department of Water & Sanitation (Link broken - http://www.dwaf.gov.za/Projects/WARMS/)
 
            - Pegasus Institute: Priority General Authorizations in rights-based water use authorization in South Africa (Link broken - http://pegasysinstitute.org/wp-content/uploads/2014/09/Priority-General-Authorisations-in-rights-based-water-use-authorisation-in-South-Africa.pdf)
 
            - IWMI: Malawi
 
            - IWMI: Kenya
 
            - IWMI: Zimbabwe
 
        
         
        - Contract with excavator for construction of surface water diversion structure and or canals
        
        
 
        - Oversee construction of water wells to project specifications.
        
        
 
        - Purchase and acquisition of surface water pumps and electrical wire based on project specifications.
        
        
 
        - Oversee completion, installation and startup of surface water pumps.
        
        
 
    
     
back to roadmap
 
 
3. Select Personnel
back to roadmap
 
 
4. Purchase Equipment
    - Valley Product Catalog  
 
back to roadmap
 
 
 
5. De-bush Pivot & Building Sites 
    - Mapping out obstacles and Field Shapes pg 27 of “Center Pivot Design” by Irrigation Association
 
back to roadmap (Link broken - https://unl.box.com/s/qt0dnlaxjqsdazw8gs6zwsfzzcnwpuzo)
 
 
6. Erect Buildings and Housing
back to roadmap
 
 
7. Erect Pump Houses & Install Equipment 
    - Irrigation Association: Planning Considerations for a New Irrigation Pump System “Pump Houses” (Link broken - http://www.golfindustryshow.com/docs/librariesprovider4/default-document-library/education/2015-sessions-presentations/planning-considerations-for-a-new-irrigation-pump-system-by-the-irrigation-association.pdf?sfvrsn=2)
 
    - Pump Installation pg 187-198 (Link broken - https://unl.box.com/s/g410dta74p0lw284fo7bleo81a0mw35o)
    
        - Pump Start-up pg 199 (Link broken - https://unl.box.com/s/9feijhown8bk9cug2w80jswm6oicicbv)
 
    
     
    - Nozzle and Sprinkler Configuration pg 97
    
        - Valley Irrigation Sprinkler Types (Link broken - http://www.valleyirrigation.com/valley-irrigation/us/irrigation-products/sprinklers)
 
        - Updating your Pivot Sprinklers (Link broken - http://blog.valleyirrigation.com/valley-irrigation/us/mediaroom/growing-the-conversation-blog/blog-home/update-your-center-pivot-to-perform-as-good-as-new)
 
        - From Pump to Pivot Handout (Link broken - https://unl.box.com/s/013xm3q90zrkamfgedzzylin0rtiahwl)
 
    
     
back to roadmap
 
 
8. Install Piping
    - Pivot System Piping
    
        - PolySpan: Superior Irrigation Pipes (Link broken - http://www.valleyirrigation.com/valley-irrigation/us/irrigation-products/polyspan)
 
        - Valley Pivot Design Guides: Selecting Piping and Pipe Installation (Link broken - https://unl.box.com/s/9bsq9ikve2huwlcv72jumhjpaehx4yuj)
 
    
    
     
back to roadmap
 
 
9. Purchase & Ship Equipment
back to roadmap
 
 
10. Erect Pump Houses & Install Equipment 
back to roadmap
 
 
11. Purchase & Ship Storage/Post-Harvest Equipment 
back to roadmap
 
 
12. Purchase & Ship Equipment
back to roadmap
 
 
 
13. Begin Production Operations
back to roadmap